Hi Michael, Please review my post regarding Rollover Sequence
and comment:
http://support.iambic.com/forum/showthread.php?t=37459
As noted, for me on AGPro 13.03 1030, any task that has a Rollover Sequence skip day defined does not rollover. In List View, Standard Mode, that task becomes past due and does not increment to the next day.
For j_rahe (on German Agendus, V13 build unclear), in 1 Day View:List Mode, the task with a rollover sequence appears on the rollover skip day as Past Due. Then, on the next non-skip day, the task is no longer past due.
1. How is Rollover Sequence, skip days supposed to work?
- Should a task with a rollover sequence display as Past Due
on a skip day ?
- Or should the task rollover past skip day(s) and display as
current on the next non-skip day ?
Thanks for your help.